Site:Service Station, Kent
Scope of works: Demolish former service station, including canopy, removal of all underground storage tanks, demolish outlying properties including 2 detached houses , grade over site, environmental investigations working with environmental consultants, new site boundary fencing
Client: ABB, Environmental Services
Duration: 13 weeks

Site:Fuel Terminal, Essex
Scope of works: Site set up, site investigation works including trial pits and vacuum excavation across a large area of the site working with the environmental consultants. This project is ongoing and further works are planned for later this year
Client: Arcadis
Duration: 5 weeks

Commercial Build of M.O.T Workshops and Offices

Site:Boundary Service Station, Enfield
Scope of works: To work alongside throughout the duration of the project the current Gulf petrol station forecourt and retails shops. The site has limited space and access and we will be working with nearby properties and businesses
Removal of former building concrete slab and footings, crush and recycle materials. New foundations and ground works. Steel frame install with cladding and block work, for a modern MOT workshop and offices. Project due for completion April 2015.
Client:Boundary Service Station
Duration: 16 weeks

Design & Build of Petrol filling station

Site:Service Station, Enfield
Scope of works: Set up temporary offices for client at the front of the site, Demolish current petrol station, break out all old services and footings, new foundations, piling, ground works, steel frame, building state of the art petrol station with new MOT center with office space on the first floor
Client:Empire Garages Ltd
Duration: 24 weeks

Fuel line replacement

Site:Service station, Oxfordshire
Scope of works:Breaking out concrete and removal of old pipe work. Excavating from forecourt fuel tank farm to fuel pumps and interceptor, installation of new pump islands, traffic management system, vent stack and pipe work.
Client: Gilbarco Veedoroot
Duration: 4 weeks

Mothballing

Site:Service station, Cambridgeshire
Scope of works: In the last few years there has been an increasing demand within the industry for mothballing services. Our specialist team offers this service to our customers. This service also means that the site can be handed back to the landlord or be ready for full demolition or redevelopment of the site.
Client: URS Environmentals
Duration: 1 week

Forecourt Maintenance

Site: Various sites accross the UK
Scope of works: Maintenance & repair to the fuel terminal and forecourt operations, drainage channel and forecourt drainage, interceptor installation and repairs, new tank excavations and installation, trenching excavations Re surfacing, tarmac or concrete repairs, reinforced concrete bays for tanker stands , pole signs or above ground tank installations, pump islands, stainless steel surround, moulded concrete or kerbed manhole chamber repairs, modifications or chamber lid replacement
Client: Various major oil companies and private forecourt owners